Road Improvements to Ferrell Parkway to Begin This Sunday the 5th

Friday, March 03, 2017

Virginia Beach Public Works has announced that crews will begin road improvements to Ferrell Parkway this Sunday, March 5th.

The project will include milling, paving and pavement marking work on both eastbound and westbound Ferrell Parkway from Indian River Road to Indian Lakes Boulevard at Parkway Place Market Shopping Center; and from southbound Princess Anne Road from the Salem Road overpass to Lynnhaven Parkway.

Work will be from 7 p.m. to 5 a.m. each evening.

All night time milling will be from 7 p.m. to 5 a.m.  Any paving and marking work that needs to be done during the weekday hours will be from 9 a.m. until 3 p.m.  Any weekend work – if needed – will be scheduled between the hours of 7 a.m. and 5 p.m.

The project is likely to produce traffic delays, congestion and some construction noise.  Advanced warning signs will be clearly posted advising motorists of lane closures.  Citizens are urged to use alternate traffic routes when possible.

The work is expected to be completed by March 25, 2017.

All scheduled work is weather permitting.

For additional information, please contact Dan Kiley or Dennis Simon at 385-1470.


ferrell-pky-sm-3-2017.jpg


​​​​​​​​​​​​​​​​