Burton Station Phase 1

​​​​Project Summary

Burton Station Phase​ 1 includes design and construction of an improved section of Burton Station Road from Northampton Blvd. to approximately the midway point to Miller Store Rd. as well as a segment of a new north/south road (Tolliver Rd., formerly called Golf Rd.) intersecting with Burton Station Rd. and extending 100 feet in either direction.  Improved road sections will include two lanes with curb and gutter, sidewalks and street lights.  A new pump station and water and sewer lines will also be installed.

Schedule

Project Activity ​Begin Date ​Completion Date
​DesignApril 2010​March 2012​
​Site AcquisitionApril 2012​March 2014​
​Construction​July 2014August 2015​