COMMENT SHEET FILLABLE FORM SPlazaTrl.pdf Overview
Windsor Woods, Princess Anne Plaza and The Lakes are neighborhoods located in what was

once the undeveloped headwaters of the Lynnhaven River. According to aerial photos from 1949, the area was originally forest surrounded by farmland. Much of the area has relatively low elevations. This coupled with increasing sea levels (approximately 1-foot over the last 50 years) and the increasing frequency of storms with significant tides and rainfall amounts, has resulted in severe flooding of the neighborhood during these storm events. The City has funded and completed a number of drainage improvement projects over the years (see the section “Past Drainage Improvement Projects”); a number of drainage improvement projects are currently underway or will be starting soon (see the section “Current Drainage Improvement Projects”); and, beginning with the FY18 budget, the City Council has established initial funding to develop a multi-year program of projects to comprehensively address flooding in Windsor Woods, Princess Anne Plaza and The Lakes.
For
questions or comments or to be added to the newsletter distribution list, please contact us via email at:
papww@vbgov.com.
Please include your contact information when emailing us.
Past Drainage Improvement Projects
- Canal Number 2 Improvements, CIP 2-909: The City cost-participated with the Army Corp of Engineers to construct Canal #2. The canal extends from London Bridge to West Neck Creek. The canal helps to alleviate flooding in and around Princess Anne Plaza and surrounding areas by diverting the stormwater runoff from London Bridge Creek to the Eastern Branch of the Lynnhaven River. The project was completed in 1990, and the total project cost was $55M.
Rosemont Road – Windsor Woods Drainage, CIP 7-115: This project included the construction of two stormwater detention ponds; one on the Bow Creek Golf Course and another along Rosemont Rd. adjacent to St. Francis Episcopal Church. It was completed in May 1996, and the total project cost was $1.2M.
Princess Anne Plaza Drainage Phase 2, CIP 7-114: The first phase of this project included channel improvements and channel re-routing within Bow Creek Golf Course. It was completed in August 1996. The second phase included box culverts under Club House Road and Bow Creek Boulevard. It was completed in June 1998. The third phase included channel improvements from Bow Creek Boulevard to Rosemont Road and a pedestrian bridge in Northgate Park. This was completed in October 2000. The total project cost was $4.3M.
Stormwater Infrastructure Rehabilitation, CIP 7-004: This project provided inspection and rehabilitation of stormwater infrastructure. The stormwater piping system was mapped, cleaned, and repairs were made by either slip-lining pipes or pipe replacement. This was completed in 2008, and the total project cost was $5M.
Bow Creek Rec Center Storm Drainage Work, CIP 3-405: Storm drain improvements were installed with the Bow Creek Recreation Center to help drainage for the recreation center as well as provide additional storm drainage improvements for Club House Road and the immediate area. This was completed in 2015, and the total project cost was $600K.
Current Drainage Improvement Projects
- Windsor Woods Canal, CIP 7-028.002: This project dredged the 4,100-ft canal to its original capacity. The approximate 10,400 cubic yards of dredge material was removed. Construction Notice to Proceed was June, 2017 and the project was completed in March 2019. The total project cost $2M.
Windsor Oaks West – Phase I CIP 7-415: This project dredged the 1,510-ft canal to its original capacity. Approximately 4,200 cubic yards of dredge material was removed. Mobilization and dredging began in June 2017 and was completed in December 2017. The total project cost was $700K.
Windsor Oaks West – Phase II CIP 7-415: This project dredged the 2,760-ft canal to its original capacity. Approximately 7,053 cubic yards of dredge material was removed. Mobilization and dredging began in July 2017 and was completed in January 2018. The total project cost was $675K.
Windsor Oaks West – Phase III CIP 7-415: This project will dredge the 2,150-ft canal to its original capacity. The approximate volume of dredge material to be removed is 3,000 cubic yards. The first and second phases of the project are complete. The remaining phase (third phase) is anticipated to begin by March, 2020 and be completed by June, 2020. The total project cost is estimated at $625K.
Princess Anne Plaza – Northgate Ditch, CIP 7-028.001: This project dredged the 5,000-ft canal to its original capacity. Approximately 3,000 cubic yards of dredge material was removed. Construction Notice to Proceed was May, 2017 and the project was completed in May 2019. The total project cost is $2.5M.
Current Update
Michael Baker International, teamed with CDM Smith, was chosen to provide technical engineering services to:
- Develop and apply stormwater management models
- Analyze existing stormwater management infrastructure,
- Identify and recommend improvements, including the cost and phasing plans, design, preparation of construction documents, and construction phase services, for Windsor Woods, Princess Anne Plaza and The Lakes Combined Drainage Improvements (TL-PAP-WW).
The preliminary engineering reports were completed in the fall of 2019.
The following projects are being designed:
- Bow Creek Storm Water Park (Conversion of Bow Creek Golf Course into a storm water park)
- South Plaza Trail / Presidential Boulevard Drainage Improvement project
- Old Forge Road / Red Lion Road Drainage Improvement project
- Windsor Woods Storm Water Pump Station
- North London Bridge Creek Storm Water Pump Station and Tide Gate
- South London Bridge Creek Channels and Tide Gate
Detailed information about these projects is available at the following web site: FY2021-22 Proposed CIP WEB.pdf (vbgov.com)
More information about these projects is available in the banner to the right.
For questions or comments, please contact us at: papww@vbgov.com
Public Meetings for Upcoming Projects
Presentations for the following Public Meetings are available:
- The Windsor Woods Drainage Project, Old Forge Road Lion Road Drainage Improvements, November 2021
The Windsor Woods Drainage Project, South Plaza Trail and Presidential Boulevard Drainage Imrpovements, November 2020
Princess Anne Plaza
Drainage Project: Bow Creek Stormwater Park, October 2019
The Lakes, Princess Anne Plaza, and Windsor Woods Combined Drainage Project Program Overview, November 2018
The Windsor Woods Drainage Project, Thalia Creek Tide Gate, November 2018
The Windsor Woods Drainage Project: Club House Road, February 2019