Lesner Bridge Replacement

​​​​​​​​​​​​​​​​​​
Rendering of the Completed Lesner Bridge Structure

Construction Cam​​era

A construction camera​ has been installed to view images of the bridge construction.  Images are updated on the hour.​

June 30, 2017 Update

Folks:  
Last week we successfully accomplished a major milestone in the project – moving the gantry crane from the north side of Shore Drive to the south side of Shore Drive and into position to begin assembly of the eastbound bridge superstructure segments.  To do this, we had to close Shore Drive and setup a long detour until the move could be completed.  The last piece of this move is to remove the two beams that are currently located on the western end of the bridge crossing Shore Drive. 
 
Unlike the first two phases of this gantry crane move, a detour WILL NOT be required to remove these two beams.  Next Thursday July 6, beginning at 12:01 AM and ending at 4:00 AM Shore Drive at Lesner Bridge will be reduced to a single lane and a flagger operation will control the direction of traffic across the bridge.  Therefore, motorists should be PREPARED TO STOP on their approach to the bridge during this time period.  Bridge crossing delays of up to 15 minutes should be expected and motorists may want to plan an alternate route while these two beams are removed.






Area of Work and Restricted Traffic on Lesner Bridge July 6, 2017 12:00 AM to 4:00PM





Please note that on Wednesday July 5th, 2017 beginning at 10:00 PM Shore Drive at Lesner Bridge will be reduced to a single lane in each direction in preparation for the flagger operation that will begin at midnight.  

​We appreciate your patience regarding these traffic interruptions along Shore Drive at Lesner Bridge!

Have a Happy and Safe Independence Day!  …and of course Please Drive Safely!

-Chris​

Hi​​​story

This project first appeared in the FY 2002-03 CIP and is included in the Governor’s Transportation Plan. Lesner bridge was identified for replacement through the City’s bridge condition inventory and the Shore Drive Transportation Study.  In VDOT’s final FY2014 six-year plan, the State shifted prior VDOT funding to out years, but requested the City maintain the prior schedule.  The City Council approved substitution of contractual obligation debt on August 13, 2013 so the project could be bid for construction, with agreement that VDOT would provide $10,453,200 in FY 2014-15, $13,000,000 in FY 2016-17, and $14,220,117 in FY 2017-18 and the local debt would be decreased in those years accordingly.  Bid were opened on December 21, 2013 and the construction contract executed with McLean Construction on April 28, 2014.  The Notice to Proceed for construction was issued for June 2, 2014. 

Work Description

This project will replace the existing Lesner Bridge with a signature facility that is capable of handling six lanes of traffic in the future. The replacement bridge structure will be striped for two lanes of traffic and wide shoulders.  The inside lane will be 12 feet wide and the inside shoulder will be 6 feet wide.  The outside lane will be 14 feet wide and the outside shoulder will be 8 feet wide. Each bridge will also have a 10 foot wide multi-use path for use by pedestrians and recreational cyclists. The proposed bridge will be designed to provide minimum 45 feet vertical clearance above mean high water and 225 feet minimum horizontal clearance at center navigation channel span. This project also includes upgrades to the intersections of East Stratford Street and Vista Circle (the termini for the project), as well as aesthetic upgrades within the project limits.


McLean Construction, Inc. began the project June 2, 2014.

As a reminder, the sidewalk on westbound Shore Drive is closed to pedestrians and cyclists between Page Avenue and East Stratford Street.  If pedestrians need to cross the bridge, they will need to cross the eastbound bridge where a temporary 4-foot wide pedestrian/cyclist access has been provided.​

PLEASE DRIVE SAFELY!

Additional information is available on the Lesner Bridge Project Detail Sheet​

​​​Select Lesner Bridge Replacement Project Archive​ to view past updates for this project.​​​​​​

​​​