UPDATE #3 – Arctic Avenue Road Closure Schedule


Release Date:  Friday, October 2, 2009  2:45 p.m.

Due to unforeseen circumstances, the original schedule of road closures for the first phase of construction of the Laskin Road Gateway project has been modified. The following is an updated road closure schedule that will be in effect during Phase 1 of construction, from Sept. 8, 2009 through May 31, 2010. 

 

Closed from Sept. 8, 2009 through Nov. 1, 2009

Arctic Avenue: 32nd Street to Laskin Road/31st Street

 

Closed from Sept. 8, 2009 through May 31, 2010

Arctic Avenue: 27th Street to 30th Street

 

Closed from Sept. 28, 2009 through Nov. 1, 2009

Intersection of 32nd Street and Arctic Avenue

 

Closed from Sept. 28, 2009 through Dec. 31, 2009

32nd Street: Holly Road to Arctic Avenue

 

Closed from Oct. 1, 2009 through Nov. 1, 2009

Intersection of 30th Street and Arctic Avenue

32nd Street from Arctic Avenue to Pacific Avenue

 

Closed from Oct.1, 2009 through May 31, 2010

Arctic Avenue from 30th Street to Laskin Road/31st Street

 

Closed from Nov. 1, 2009 through Dec. 31, 2009

Intersection of 32nd Street and Holly Road

 

Closed from Jan. 1, 2010 through March 17, 2010

Intersection of Laskin Road/31st Street and Arctic Avenue

 

Closed from Jan. 1, 2010 through May 31, 2010

Arctic Avenue: 32nd Street to Laskin Road/31st Street

 

Warning signs have been posted advising motorists of detours, and construction schedules may change based on the weather or other unforeseen events.

 

For additional information, please contact John McDonald, P.E., project manager with the Department of Public Utilities, at 757-385-4171.

 

                                                                                       ###

 

                                                UPDATE #2 – Arctic Avenue Road Closure Schedule

 

Following is a revised closure schedule for Arctic Ave., which marks the start of the first phase of the Laskin Road Gateway project. This information supersedes all previous news releases issued. Changes are bolded.  

 

Warning signs will be posted in advance to advise motorists of detours, and construction schedules may change based on the weather or other unforeseen events.

 

Sept. 8 – Dec. 31, 2009

Arctic Ave. from 32nd St. to Laskin Rd.

Arctic Ave. from 27th St. to 30th St.

32nd St. from Holly Rd. to Arctic Ave.

Intersection of 32nd St. and Arctic Ave.

 

Oct. 1, 2009 – Dec. 31, 2009

Intersection of 30th St. and Arctic Ave.

           

Oct. 1, 2009 – May 31, 2010

Arctic Ave. from 30th St. to Laskin Rd.

 

Jan. 1, 2010 – March 17, 2010

Intersection of Laskin Rd. and Arctic Ave.

 

March 18, 2010 – May 31, 2010

32nd Street from Arctic Ave. to Pacific Ave.

 

                                                                                      ###

 

 

296sga update 3

 

Media Contacts:

John McDonald
(757) 385-8166

Katie Rider
(757) 385-4171

More News...